Construction project:
Schaan-Vaduz Youth Hostel
Start of construction for the new Schaan-Vaduz Youth Hostel
In 2015, we decided that Schaan-Vaduz Youth Hostel, which required renovation, would be replaced by a new building. On 4 July 2018, the winner of the architectural competition was announced: the architectural office Erhart + Partner AG prevailed against a total of 19 competitors with its Einstein project, and will be responsible for the new building. The total costs for the construction project will amount to around CHF 9.1 million. On the 08th of November 2019 the construction could be started.
To the press release from the 04.07.2018 (only in German)
-
Conversion: a timeline
-
-
31. DEC. 2015
In 2015, it was decided that Schaan-Vaduz Youth Hostel, which required renovation, would be replaced by a new building.
31. MAR. 2018In March 2018, the Schaan and Vaduz municipalities advertised an international project competition on behalf of the Schaan-Vaduz youth hostel foundation, for which 22 architectural firms were ultimately approved.
-
04. JUL. 2018
The winner of the architectural competition was announced: the architectural office Erhart + Partner AG prevailed against a total of 20 competitors with its Einstein project, and will be responsible for the new building.
16. JUL. 2018All 20 competition projects were put on display to the public from 11 to 16 July 2018 in the small hall of SAL in Schaan.
-
-
Conversion: a timeline
-
-
01. SEP. 2018
The pre-project phase of the new construction will begin in September 2018.
08. JUL. 2019The official planning permission was granted by the Liechtenstein Office for Construction and Infrastructure.
-
01. NOV. 2019
Construction is scheduled to begin in November 2019.
19. AUG. 2020The first construction machines were started up at Under Rüttigass 6 in Schaan in November 2019, and the Schaan-Vaduz Youth Hostel is now celebrating its topping out.
-
-
Conversion: a timeline
-
-
01. APR. 2021
After around one and a half years of construction, the new Schaan-Vaduz Youth Hostel will welcome its first guests in spring 2021.
-
-
Conversion: a timeline
-
Conversion: a timeline
31. DEC. 2015In 2015, it was decided that Schaan-Vaduz Youth Hostel, which required renovation, would be replaced by a new building.
31. MAR. 2018In March 2018, the Schaan and Vaduz municipalities advertised an international project competition on behalf of the Schaan-Vaduz youth hostel foundation, for which 22 architectural firms were ultimately approved.
-
Conversion: a timeline
04. JUL. 2018The winner of the architectural competition was announced: the architectural office Erhart + Partner AG prevailed against a total of 20 competitors with its Einstein project, and will be responsible for the new building.
16. JUL. 2018All 20 competition projects were put on display to the public from 11 to 16 July 2018 in the small hall of SAL in Schaan.
-
Conversion: a timeline
-
Conversion: a timeline
01. SEP. 2018The pre-project phase of the new construction will begin in September 2018.
08. JUL. 2019The official planning permission was granted by the Liechtenstein Office for Construction and Infrastructure.
-
Conversion: a timeline
01. NOV. 2019Construction is scheduled to begin in November 2019.
19. AUG. 2020The first construction machines were started up at Under Rüttigass 6 in Schaan in November 2019, and the Schaan-Vaduz Youth Hostel is now celebrating its topping out.
-
Conversion: a timeline
-
Conversion: a timeline
01. APR. 2021After around one and a half years of construction, the new Schaan-Vaduz Youth Hostel will welcome its first guests in spring 2021.